Wednesday, September 11, 2024

11.9.2024 Wednesday - setting deadlines


At the Renna meeting this morning, we set deadlines for the completion of the project; Dec 2024 although they have not included much of the M&E components. Testing and commissioning can be such a pain, and this morning there were some lighting conduits which we were not happy with. Our main contractor's site manager looks weary, I tell her we are close to the end. 

Meanwhile, Sean and Jenny are at Singgahsana for the test piles, he shared photos in the family website. 


Back in the office, Fiona is back and we set deadlines for the new project:                                  18.9.2024 (Wed) - issue draft architectural layouts to client and appointed consultants. (M&E, C&S, Planner, Surveyor) for their feedback.                                                                                          
26.9.2024 (Thurs p.m.) - Client-consultants meeting to discuss:
a. deadlines for submissions/approvals; DID, SEB, SPA
b. project phasing
c. design review: architecture, C&S, M&E, planning, strata matters.                                                      10.10.2024 (Thurs) - CCM #2 - DID, SEB submitted. Draft SPA set
24.10.2024 (Thurs) -eSPA submitted.

I like it (after she corrected my dates) - while I was already at tennis.